MBSA 入伙纸 简介
- CFO(Certificate of Fitness for Occupation)或CCC(Certificate of Completion and Compliance)是莎阿南市政厅(MBSA)签发的法律文件,证明建筑在完工后安全且适合居住或使用,符合当地建筑规范及法规要求。
相关政府部门
- 莎阿南市政厅(Majlis Bandaraya Shah Alam,MBSA)
执照名称(马来文)
- Sijil Layak Menduduki (CFO) / Sijil Siap dan Pematuhan (CCC)
详细信息
- CFO或CCC证明建筑已根据批准的设计建造,并符合安全、结构及使用标准。
- 适用于MBSAJ辖区内的新建工程、重大装修或扩建项目。
- CCC由认证专业人士(建筑师/工程师)签发,而CFO由MBSA批准发放。
- 必要检查包括结构、水管、电气及消防安全合规性。
重要规则
- 未取得CFO或CCC,禁止占用或使用建筑物。
- 建筑施工必须遵守所有已批准的设计、材料及安全标准。
- 对建筑设计的任何更改必须事先获得MBSA批准。
- 所有相关费用及税款必须在CFO/CCC发放前缴清。
违规与惩罚
- 未持有效CFO或CCC占用建筑物可能导致: RM 1,000至RM 50,000的罚款。
- 不遵守MBSA建筑规范或法规可能导致: 法律诉讼或拆除令。
- 额外处罚可能包括暂停进一步施工活动及移除未经授权的结构,费用由业主承担。
法律顾问
Penny Lim , 法律顾问
Penny女士专注于识别潜在法律问题,并在政府法规、消费者保护及公平雇佣领域提供解决方案。她的主要职责包括:
提供关于政府及商业许可的法律建议。
在签署文件前审查法律文件。
根据公司需要完成法律研究。
Commonly Asked Questions
The MBSA CFO (Certificate of Fitness for Occupation) / CCC (Certificate of Completion and Compliance) is an official certification confirming that a completed building is safe, structurally sound, and complies with MBSA regulations before it can be occupied.
The purpose of the CFO/CCC is to:
- Ensure public safety and structural integrity of buildings
- Confirm the construction follows approved plans and specifications
- Prevent illegal or unsafe occupation of buildings
- Ensure compliance with building codes, fire safety, and utility standards
Property developers, contractors, architects, or building owners must apply for a CFO/CCC before any completed building can be legally occupied.
- CCC is issued by a certified professional such as an architect or engineer as confirmation that the building complies with all requirements.
- CFO is issued directly by MBSA after reviewing compliance documentation and site inspections.
It is required for:
- New building constructions
- Building extensions
- Major renovations affecting structural, safety, or approval elements
- Any premises intended for residential, commercial, or industrial use
Typical inspections include:
- Structural compliance
- Plumbing and sanitary systems
- Electrical safety
- Fire safety system approvals
- Building materials compliance
- Accessibility standards (if applicable)
Timelines vary depending on documentation completeness, inspection results, and project size. The process may take several weeks to a few months.
No. Occupying or using the building before approval is illegal and may result in fines, penalties, or forced evacuation.
Yes — MBSA may reject applications if:
- The building does not match approved plans
- Required inspections are incomplete
- Safety or legal non-compliance issues are found
Penalties may include:
- Fines between RM1,000 to RM50,000
- Construction stop orders
- Forced evacuation or demolition of illegal structures
- Legal action and additional compensation claims